When planning to build a home in Bengaluru, one of the biggest cost components you need to account for is labour charges. Labour costs can significantly influence your total construction budget, especially with rising material prices and urban development. In this guide, we explain 2025 labour charges in Bengaluru in detail – broken down by work type, skill level, and practical advice for clients and contractors.
Whether you’re a homeowner, a contractor, or part of a construction company, understanding these charges helps you budget effectively, plan your timelines, and ensure fair compensation for skilled workers.
🔧 Why Labour Charges Vary in Bengaluru
Labour rates are not one-size-fits-all. Charges vary depending on:
- Skill Level (Skilled, Semi-skilled, Unskilled)
- Nature of Work (Masonry, Electrical, Plumbing, Carpentry, etc.)
- Work Type (Daily wage, Per sq.ft, or Contract-based)
- Project Size and Complexity
- Location (Central vs. Peripheral Bengaluru)
- Experience and Team Size

👷 Types of Labour in Construction
- Skilled Labour: Includes electricians, plumbers, carpenters, tile layers, bar benders, and painters.
- Semi-skilled Labour: Helpers to skilled workers or those with some experience in basic tasks.
- Unskilled Labour: General helpers for carrying materials, cleaning, and support work.
💰 Labour Charges in Bengaluru – 2025 (Approximate Rates)
Here’s a breakdown of current (2025) labour charges in Bengaluru, based on industry standards and ongoing market trends:
1. Masonry Work (Civil Mistri Charges)
Work Type | Rate Type | Rate (INR) |
---|---|---|
Brick Work (Red bricks / Concrete blocks) | Per sq.ft | ₹30 – ₹45 |
RCC Slab Shuttering | Per sq.ft | ₹22 – ₹30 |
RCC Slab Centering + Concreting | Per sq.ft | ₹45 – ₹60 |
Plastering | Per sq.ft | ₹22 – ₹30 |
Daily Wage for Mistri | Per day | ₹900 – ₹1,400 |
Helper (Mazdoor) | Per day | ₹600 – ₹800 |
2. Bar Bending (Steel Work)
Work Type | Rate Type | Rate (INR) |
---|---|---|
Cutting, Bending & Tying Steel | Per ton | ₹8,000 – ₹12,000 |
RCC Column/Beam Steel Work | Per sq.ft (built-up) | ₹15 – ₹20 |
3. Carpentry Work
Work Type | Rate Type | Rate (INR) |
---|---|---|
Door/Window Frame Fitting | Per piece | ₹600 – ₹900 |
Modular Kitchen & Wardrobes | Per sq.ft | ₹400 – ₹750 |
Plywood Furniture Works | Per sq.ft | ₹350 – ₹600 |
Daily Wage | Per day | ₹1,000 – ₹1,500 |
4. Electrical Work
Work Type | Rate Type | Rate (INR) |
---|---|---|
Wiring (points incl. conduit, box) | Per point | ₹300 – ₹500 |
Switchboard/MCB panel fitting | Per unit | ₹300 – ₹600 |
Labour Only (Electrician) | Per day | ₹900 – ₹1,400 |
5. Plumbing Work
Work Type | Rate Type | Rate (INR) |
---|---|---|
Bathroom/Kitchen Plumbing – Labour | Per unit (bathroom/kitchen) | ₹7,000 – ₹12,000 |
Pipe laying (PVC/CPVC) | Per running ft | ₹15 – ₹30 |
Labour Only (Plumber) | Per day | ₹900 – ₹1,300 |
6. Painting Labour Charges
Work Type | Rate Type | Rate (INR) |
---|---|---|
Interior Painting (Labour Only) | Per sq.ft | ₹10 – ₹15 |
Exterior Painting | Per sq.ft | ₹12 – ₹20 |
Putty + Primer + Paint | Per sq.ft | ₹20 – ₹35 |
🧾 How Labour Charges Are Usually Structured
Construction companies and individual contractors in Bengaluru offer labour services in three common structures:
- Per Square Foot Rate
- Ideal for clearly defined scope of work.
- Preferred in plastering, tiling, or brickwork.
- Per Day (Daily Wage)
- Common for support labour, site cleaners, or small custom works.
- Risk of delay if not managed properly.
- Contract Basis (Labour + Material or Labour Only)
- Best for large projects. Enables milestone payments and accountability.
- Used for full house construction or large-scale MEP works.
📌 Tips for Homeowners Hiring Labour
- Avoid Unverified Labour: Always go through a reputed construction company or agency.
- Draft a Labour Contract: Clearly define the scope, payment schedule, working hours, and deadlines.
- Account for Delays: Rain, material delays, or skill availability can affect timelines.
- Monitor Quality: Assign an engineer or supervisor to monitor and guide.
- Beware of Underquoting: Low labour charges might mean compromise in quality.

🏗️ How Our Construction Company Ensures Fair Labour Practices
At [Your Company Name], we maintain transparency and fair pay as core principles. Our labourers are:
- Paid industry-standard rates based on skill and work type.
- Trained periodically on safety and workmanship.
- Provided with proper PPE and site conditions.
- Scheduled systematically to avoid project delays.
Our contracts include detailed labour cost breakdowns, so clients know exactly where their money is going. We ensure both quality construction and humane work culture.
📞 Need Help Estimating Labour Costs for Your Home?
We offer free construction estimates and site visits across Bengaluru. Whether you’re building from scratch or planning a renovation, our team is ready to help you plan the right labour strategy for your budget and timeline.
Contact us today to schedule your consultation or download our full Labour Rate Card for 2025!